We have received a further update from the City of Port Phillip on the closure of the boat landing next to Mr Hobsons and D'lish Fish on Station Pier:
Contractors will be commencing works to repair the failed piles next Monday, 17th January. The works commencement was slightly delayed and based on the current schedule provided, we anticipate these works to be completed by 4th March. Parks Victoria have been advised and will be issuing a notice to mariners. Additionally, the St Kilda Ferry service will continue to operate from the Eastern promenade throughout the works and the contractors have been advised of their schedule to avoid any conflicts and ensure their safety.
Further inspections are also being undertaken currently on the Eastern and Southern promenades to inform their detailed condition and any relevant findings will be shared once these are completed.